Analisis Time-Cost Trade Off Pada Percepatan Struktur dan Arsitektur, dengan Metode Cast In Situ dan Precast terhadap Efisiensi Waktu dan Biaya (Studi Kasus RSUD Dr.Loekmonohadi Kudus) 27 35

Authors

DOI:

https://doi.org/10.26623/ijces.v3i2.16143

Keywords:

Time cost trade off, Cast in situ, Precast, Cost slope, Relative importance index

Abstract

High-rise building projects frequently experience schedule delays when field progress falls behind the baseline S-curve, so acceleration is required to restore the planned completion date. Overtime on cast in situ work, the most common approach, is constrained by concrete curing time and by declining productivity due to worker fatigue; precast concrete is therefore considered as an alternative. This study compares both acceleration schemes for the structural and wall works of the Stroke and Oncology Building, RSUD dr. Loekmonohadi Kudus, using the Time Cost Trade Off (TCTO) method. Secondary data (bill of quantities and time schedule) were analysed with the Critical Path Method (CPM) and cost slope, while primary data from questionnaires completed by 34 respondents were analysed using the Relative Importance Index (RII). Both schemes shorten the project duration from 136 to 109 days (27 days or 19.85%); at activity level, precast reduces the cumulative duration of structural and wall works from 350 to 154 days (56%). At 109 days, the overtime scheme yields a total cost of Rp19,130,607,056.57 (+6.54%), whereas the precast scheme yields Rp21,107,070,024.00 (+17.55%), with cost slopes of Rp50.69 million/day and Rp123.90 million/day, respectively. Respondents rated the weather vulnerability of cast in situ work (RII = 0.83) and the controlled quality of precast elements (RII = 0.82) as the most important factors. Overtime is the least-cost option to reach the 109-day target, while precast is recommended when schedule certainty, work safety, and minimal disturbance to hospital operations are prioritized, provided that heavy-equipment mobilization and factory supply are properly planned.

Downloads

Download data is not yet available.

References

Ardiansyah, O. Y., Gunasti, A., & Yanuar, S. F. (2025). Efektivitas Pekerjaan Beton Precast Dan Konvensional Pada Pekerjaan Struktur Bangunan 2 Lantai. Jurnal Smart Teknologi, 6(5), 588–602.

Armalisa, A. (2021). Metode Crashing Terhadap Penambahan Jam Kerja Optimum Pada Proyek Konstruksi. Jurnal Teknik Sipil Universitas Serang Raya (CIVTECH), 1(1), 41–58.

Awaliah, F., Nurasiyah, S., & Istiqomah, I. (2021). Analisis Perbandingan Waktu dan Biaya Konstruksi Beton Menggunakan Metode Cetak di Tempat dan Pracetak. Kokoh, 19(2), 99–108.

Bere, C. R., Messakh, J. J., & Edyan, R. (2025). Analisis Perbandingan Metode Konstruksi Precast Concrete dan Concrete Cast-In-Place Pada Gedung Bertingkat. Jurnal Batakarang, 6(2a), 45–52.

Dayunita, W., Pramanda, H., Ariansyah, D., & Bunyamin, B. (2024). Analisa Penambahan Waktu Kerja (Jam Lembur) Terhadap Biaya Pelaksanaan Proyek dengan Metode Time Cost Trade Off (Studi Kasus Gedung Badan Kepegawaian Aceh). Journal of Planning and Research in Civil Engineering, 3(3), 452–458.

Fakhrulloh, Z. A., & Triana, M. I. (2025). Optimasi Waktu Proyek Konstruksi Dengan Penambahan Jam Kerja Menggunakan Metode Crashing (Studi Kasus: Proyek Pembangunan Gedung Pusat Terpadu RSUD Sidoarjo). Jurnal Teknik Industri Terintegrasi, 8(1), 112–124.

Fardila, D., & Adawyah, N. R. (2021). Optimasi Biaya Dan Waktu Proyek Konstruksi dengan Lembur Dan Penambahan Tenaga Kerja. INERSIA: Informasi dan Ekspose Hasil Riset Teknik Sipil dan Arsitektur, 17(1), 35–46.

Husen, A. (2021). Manajemen Proyek: Perencanaan, Penjadwalan, dan Pengendalian Proyek. Yogyakarta: Andi.

Khiyana, A., Sundari, T., Yulianto, T., Nugroho, M. W., & Agung, A. I. (2025). Analysis and Risks Fast Track And Crash Program Method on Building Project. Jurnal Pensil: Pendidikan Teknik Sipil, 14(1), 154–168.

Koesoema, H., Kushartono, W., & Prabowo, A. (2023). Analisis Penggunaan Beton Pracetak di Proyek Pembangunan Mall XYZ Kota Wisata. JMTS: Jurnal Mitra Teknik Sipil, 6(2), 407–414.

Peraturan Presiden Republik Indonesia Nomor 16 Tahun 2018 tentang Pengadaan Barang/Jasa Pemerintah. (2018). Jakarta: Sekretariat Kabinet Republik Indonesia.

Putra, E. A., Putra, I. N. D. P., & Puspitasari, N. D. (2026). Analisis Perbandingan Dinding Precast Dan Bata Ringan Terhadap Waktu dan Biaya Pada Facade Proyek Pakuwon Residence Bekasi Mixed Use Development. Briliant: Jurnal Riset dan Konseptual, 11(1), 237.

Soeharto, I. (1997). Manajemen Proyek: Dari Konseptual sampai Operasional. Jakarta: Erlangga.

Werdana, S. D., & Priyanto, B. (2023). Analisis Percepatan Waktu dan Biaya Proyek Konstruksi Dengan Penambahan Jam Kerja (Lembur) Menggunakan Metode Time Cost Trade Off. Journal of Comprehensive Science, 2(7).

Zhaputro, M. A. D., Darjanto, H., & Nugrahini, F. C. (2024). Penerapan Metode Time Cost Trade Off untuk Optimasi Biaya Dan Waktu Pada Pengaruh Redesign Struktur Bawah (Studi Kasus: Proyek Pembangunan Klinik Utama Mata JEC Java @Pasuruan Tahap 1). Journal of Manufacturing in Industrial Engineering & Technology, 3(2), 93–106.

Downloads

Published

2026-10-23

Issue

Section

Articles

How to Cite

Analisis Time-Cost Trade Off Pada Percepatan Struktur dan Arsitektur, dengan Metode Cast In Situ dan Precast terhadap Efisiensi Waktu dan Biaya (Studi Kasus RSUD Dr.Loekmonohadi Kudus). (2026). Indonesian Journal of Civil Engineering Study, 3(2), 46-60. https://doi.org/10.26623/ijces.v3i2.16143