Analisa Perencanaan Pembangkit Listrik Tenaga Surya Atap dengan Sistem Hybrid di PT. Koloni Timur
DOI:
https://doi.org/10.26623/elektrika.v14i1.3784Keywords:
PLTS, Hybrid, PT East ColonyAbstract
This study discusses the Planning of a Rooftop Solar Power Plant with a Hybrid System at PT East Colony Kudus. The
model is set as a PLTS whose solar panels are adjusted to the roof area of the building. This PLTS is functioned as a new
renewable energy resource (EBT) in the form of a hybrid between PLTS and PLN's electrical energy source, this is done to
help supply electricity. Parameters determined include: roof area, solar panel capacity, inverter capacity, battery capacity
and payback period. The results show that PLTS with a total of 80 solar panels installed with a capacity of each panel 405
Watt peak, then obtained a power capacity of 32.4 kilo Watt peak which is divided into 5 arrays, with a solar charger controller
and inverter using a 10kW capacity of 5 units, 80 batteries with a capacity of 400Ah. So that PLTS is able to contribute 39.3%
of the total power needed by PT East Colony (electric power from PLN is 60.7%). This hybrid payback period will return after
8 years and 7 months.
Downloads
References
C. S. Iskandar and N. Latief, Sistem Listrik Tenaga Surya
DIsain,dan Operasi Instalasi. Sleman: CV. BUDI
UTOMO, 2018.
E. Tarigan and F. D. Kartikasari, Analisis Potensi Atap
Bangunan Kampus Sebagai Lokasi Penempatan Panel
Surya Sebagai Sumber Listrik, Teknologi, p. 110, 2017.
Sigit Sukmajati and M. Hafidz, Perancangan Dan
Analisis Pembangkit istrik Tenaga Surya Kapasitas 10
MW On Grid Di Yogyakarta, Teknologi, pp. 56 57,
G. A. Sinaga, Analisis Pembangkit Listrik Sistem
Hybrid Grid Connected Di Villa Peruna Saba, Gianyar
Bali, Teknologi, vol. 6, p. 6, 2019.
T. S. Mehang, M. Santoso, and Y. Tanoto, Studi
perencanaan pembangkit listrik tenaga surya (PLTS) Di
kecamatan Ngadu Ngala, Kabupaten sumba Timur,NTT,
Teknologi, vol. 10, p. 1, 2017.
B. . M. S. ing. Ramadhani, Instalasi Pembangkit Listrik
Tenaga Surya Dos & Don ts. Jakarta: Deutsche
Gesellschaft Fur Internationale Zusammenarbeit(GIZ)
Gmbh, 2018.
S. N. Hutagalung and M. Panjaitan, PROTYPE
RANGKAIAN INVERTER DC KE AC 900 WATT,
Jurnal Pelita Informatika, vol. 6, no. 1, p. 64, 2017.
R. Pambudi, Analisa Perencanaan Pembangkit Listrik
Tenaga Surya Di Atap Gedung Aquarium & Gedung
pertemuan Wisata Bahari Pekalongan, Semarang,
Skripsi Program Studi Teknik Elektro Universitas Islam
Sultan Agung Semarang, 2018, [Online]. Available:
PLTS, Panel surya, IRR, Energi alternatif.
C. F. K. Sari, PENGARUH ANALISIS INVESTASI
TERHADAP KELAYAKAN PENAMBANGAN BATU
MANGAN DI PT. BERKAT ESA MINING, jurnal
Science Tech, vol. 4, p. 14, 2018.
Downloads
Published
Issue
Section
License
Authors who publish this journal agree to the following terms:
The author owns the copyright and grants the journal the first publication rights with the work simultaneously licensed under the Creative Commons Attribution 4.0 International License which allows others to share the work with recognition of the authorship of the work and initial publication in the journal.
Authors may enter into separate additional contractual agreements for non-exclusive distribution of the published journal version of the work (e.g., posting it to an institutional repository or publishing it in a book), in recognition of its initial publication in this journal.
Authors are allowed and encouraged to post their work online (e.g., in institutional repositories or on their websites) before and during the submission process, as it can lead to productive exchanges, as well as earlier and larger citations of published works (See The Effects of Open Access).
This work is licensed under the Creative Commons Attribution 4.0 International License.